CDD frequently provided applicants with incremental or successive correction notices during the plan review and permitting process whereby additional corrections or new requirements were often issued that had not been identified during prior reviews even after applicants had corrected identified deficiencies and resubmitted revised materials. This practice contributed to project delays, increased costs, and frustration among applicants and contractors, and created a perception of inconsistency and inefficiency within the permitting process.
Jury report: Behind the Devastation: Tuolumne County Community Development Department · PDF page 48
Permanent linkOfficial response
Tuolumne County
The response partially agrees that past correction practices were unsatisfactory but says procedures have changed.
Read official response · PDF page 8The response states its position and gives an explanation, so it directly engages the finding. This assessment addresses responsiveness only, not factual or legal correctness.
This review evaluates the response document. Implementation claims have not been independently verified.