Skip to content
Grand Jury Hub

Recommendation R2

Recommendation R2

The Board of Supervisors direct the Director of Public Works/County Engineer to conduct a documented cost-benefit analysis of the County’s ¾-inch Type B aggregate asphalt specification compared with alternative mix options, including mixes compatible with those produced at the local plant. (1) The analysis should include evaluation of whether aligning mix specifications, in whole or in part, with the dominant plant production mix would reduce delays and lifecycle costs without materially compromising pavement durability under local traffic and climate conditions. (2) The analysis should consider production changeover costs, crew delays, overtime, seasonal constraints, and pavement performance history. Suggested completion date May 1, 2027.

Jury report: The 680-Mile Marathon: High-Altitude Maintenance on a Low-Altitude Budget — Plumas County Roads: A Department Overview · PDF page 30

Permanent link

Official responses

No response recorded
A matching agency response has not been added to Grand Jury Hub. This does not establish whether a response was submitted or is overdue.
Back to all recommendationsExplore this cycle’s discussion questions