Skip to content
Grand Jury Hub

Recommendation R1

Recommendation R1

The Board of Directors of SVBGSA adopt and publish a written implementation schedule by December 31, 2026, identifying the specific seawater intrusion mitigation project or projects (Brackish Groundwater Restoration Project, Aquifer Storage and Recovery, or the Castroville-Eastside Canal Project) it intends to advance to construction, including estimated costs, funding sources, and target dates for permitting and groundbreaking.

Jury report: Seawater Intrusion - A Shared Problem in Monterey County · PDF page 10

Permanent link

Official responses

No response recorded
A matching agency response has not been added to Grand Jury Hub. This does not establish whether a response was submitted or is overdue.
Back to all recommendationsExplore this cycle’s discussion questions