Recommendation R1
The Board of Directors of SVBGSA adopt and publish a written implementation schedule by December 31, 2026, identifying the specific seawater intrusion mitigation project or projects (Brackish Groundwater Restoration Project, Aquifer Storage and Recovery, or the Castroville-Eastside Canal Project) it intends to advance to construction, including estimated costs, funding sources, and target dates for permitting and groundbreaking.
Jury report: Seawater Intrusion - A Shared Problem in Monterey County · PDF page 10
Permanent linkOfficial responses
No response recorded
A matching agency response has not been added to Grand Jury Hub. This does not establish whether a response was submitted or is overdue.