IT acknowledges that there are pieces of equipment that are past their End-Of-Life (EOL) still operating in the IT department. A significant amount of money was allocated in the 2025-2026 budget and is being spent to make good progress. This is an ongoing effort. A new process has been implemented and a spreadsheet identifying all equipment and its associated EOL. This allows improved monitoring and planning. The 2026-2027 budget allowance will need to include appropriate funding to maintain this status.

Jury report: Compliance and Continuity Final Report · PDF page 8

Permanent link

Official responses

No response recorded
A matching agency response has not been added to Grand Jury Hub. This does not establish whether a response was submitted or is overdue.