The detention center HVAC system poses a challenge to detention center management, contributing to uncomfortable environmental exposure for inmates, staff and visitors.
Jury report: Mariposa County Adult Detention Facility · PDF page 2
Permanent linkOfficial responses
Mariposa County Sheriff's Office
Mariposa County Sheriff's Office: Accepts and reports HVAC/electrical engineering plans completed July 5, 2024 with Public Works and KPA Group.
Read official response · PDF page 1The explicit acceptance covers the finding and supplies a dated project milestone and named participants.
This review evaluates the response document. Implementation claims have not been independently verified.
Mariposa County Board of Supervisors
Mariposa County Board of Supervisors: Agrees, describes assessment for a formal bid process, and says this work should be completed in six months.
Read official response · PDF page 17The response accepts the finding and gives a planning horizon, but the phrase this work does not clearly distinguish assessment, bidding, and completed replacement.
- Assess HVAC issues and advance a formal bid process. Owner: Mariposa County Board of Supervisors. Timing: Response says this work should be completed in the next six months; the scope of that deadline is ambiguous..
This review evaluates the response document. Implementation claims have not been independently verified.