Response says
Agrees;2022 partial dredging cost almost$1m from General Fund and did not solve underlying sedimentation.
What should residents consider about Finding MARTINEZ2609-F6: F6: The marina was partially dredged last in 2022., and the County’s response?
Audit context
Response says
Agrees;2022 partial dredging cost almost$1m from General Fund and did not solve underlying sedimentation.
Audit analysis
Dated project and funding source provide checkable basis, not independent cost verification.
Finding-response score
Document completeness and usefulness—not factual verification or a legal conclusion.
4/4
Statutory elements
6/6
Public usefulness
Dated project and funding source provide checkable basis, not independent cost verification.
Scoring confidence: high
Source pages
Public participation
Use Pol.is to discuss both the Grand Jury finding and the County’s response, see where participants agree, and add a perspective for others to consider. Participant statements do not alter this audit or verify factual claims made by any participant or source document.