Recommendation R2
By July 1, 2029, OCWD and its member agencies should monitor PFAS in groundwater and surface water sources and promptly implement PFAS treatment when response levels are exceeded. [F2, F4]
Jury report: PFAS and Public Awareness: A Closer Look at Orange County Drinking Water · PDF page 37
Permanent linkOfficial responses
Golden State Water Company
Agency position unclearDecade of groundwater monitoring with OCWD; facilities on schedule where required. Treatment selected site by site using feasibility, cost, alternative supplies and timing, not response levels alone.
Read official response · PDF page 3Decade of groundwater monitoring with OCWD; facilities on schedule where required. Treatment selected site by site using feasibility, cost, alternative supplies and timing, not response levels alone. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 3. Engagement is not independent factual, legal or implementation verification.
- Respondent describes: Continue Orange County Basin groundwater PFAS monitoring and construct/operate treatment where required. Conditions/limits: Site-by-site feasibility, cost-effectiveness, alternative supplies and timing; exceedance alone not sole driver. Source status: partially-implemented; not independently verified. Owner: Golden State Water Company. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Westminster
Agency position unclearDescribes joint monitoring, UCMR3/5, DDW orders, OCWD pilot testing and 100% capital/50% O&M policy; no specific Westminster treatment schedule.
Read official response · PDF page 3Describes joint monitoring, UCMR3/5, DDW orders, OCWD pilot testing and 100% capital/50% O&M policy; no specific Westminster treatment schedule. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 3. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue stated OCWD-linked PFAS monitoring program, including cited UCMR3/5 and DDW orders; OCWD policy funds 100% design/construction and 50% eligible O&M where described. No universal local treatment-completion date inferred. Source status: claimed-ongoing; not independently verified. Owner: City of Westminster. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
City of La Palma
Agency says implementedReports monitoring all sources with non-detect PFAS; no treatment needed asserted.
Read official response · PDF page 2Reports monitoring all sources with non-detect PFAS; no treatment needed asserted. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 2. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Monitor all city sources; reports non-detect PFAS. Source status: claimed-ongoing; not independently verified. Owner: City of La Palma. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
Serrano Water District
Agency says implementedAll-well monitoring with OCWD; C.L. Larry Pharris Jr. plant operating since February 2022 treats 100% groundwater supply.
Read official response · PDF page 2All-well monitoring with OCWD; C.L. Larry Pharris Jr. plant operating since February 2022 treats 100% groundwater supply. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 2. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: C.L. Larry Pharris Jr. plant operating since February 2022 treats 100% groundwater; all-well monitoring with OCWD. Source status: claimed-completed; not independently verified. Owner: Serrano Water District. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Huntington Beach
Agency position unclearDescribes OCWD monitoring, pilots and cost-share policy but no specific city treatment implementation date.
Read official response · PDF page 3Describes OCWD monitoring, pilots and cost-share policy but no specific city treatment implementation date. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF pages 3–4. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue stated OCWD-linked PFAS monitoring program, including cited UCMR3/5 and DDW orders; OCWD policy funds 100% design/construction and 50% eligible O&M where described. No universal local treatment-completion date inferred. Source status: claimed-ongoing; not independently verified. Owner: City of Huntington Beach. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
Mesa Water District
Agency position unclearMonitoring collaboration and DDW response if applicable standards exceeded; no specific treatment trigger/timeline commitment.
Read official response · PDF page 3Monitoring collaboration and DDW response if applicable standards exceeded; no specific treatment trigger/timeline commitment. Explicit assent/general principle alone does not supply an implementation disposition or sufficient action detail. Physical report PDF page 37; selected response PDF page 3. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Collect PFAS monitoring samples with OCWD and work with DDW if applicable standards exceeded. Conditions/limits: No reportable source detections claimed; no new treatment milestone stated. Source status: claimed-ongoing; not independently verified. Owner: Mesa Water District. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Orange
Agency says implementedEight treated operating wells; four more wells at three locations in design, construction early 2027; exceeded wells removed until treated.
Read official response · PDF page 3Eight treated operating wells; four more wells at three locations in design, construction early 2027; exceeded wells removed until treated. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 3. Engagement is not independent factual, legal or implementation verification.
- Respondent describes: Eight treated operating groundwater wells; four additional wells at three locations in design with construction early 2027 and completion by July 1, 2029. Conditions/limits: Exceeding wells removed from operation until treatment. Source status: partially-implemented; not independently verified. Owner: City of Orange. Timing: 2029-07-01.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Buena Park
Agency says implementedDescribes joint monitoring, UCMR3/5, orders and OCWD cost-share policy; no local new project deadline.
Read official response · PDF page 2Describes joint monitoring, UCMR3/5, orders and OCWD cost-share policy; no local new project deadline. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF pages 2–3. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue stated OCWD-linked PFAS monitoring program, including cited UCMR3/5 and DDW orders; OCWD policy funds 100% design/construction and 50% eligible O&M where described. No universal local treatment-completion date inferred. Source status: claimed-ongoing; not independently verified. Owner: City of Buena Park. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
Orange County Water District
Agency position unclearBasin/Santa Ana watershed monitoring UCMR3/5 and orders, pilot tests, initial-monitoring assurance and 100% capital/50% O&M policy.
Read official response · PDF page 4Basin/Santa Ana watershed monitoring UCMR3/5 and orders, pilot tests, initial-monitoring assurance and 100% capital/50% O&M policy. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 4. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue stated OCWD-linked PFAS monitoring program, including cited UCMR3/5 and DDW orders; OCWD policy funds 100% design/construction and 50% eligible O&M where described. No universal local treatment-completion date inferred. Source status: claimed-ongoing; not independently verified. Owner: Orange County Water District. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Fountain Valley
Agency says implementedJoint monitoring includes UCMR3/5 and DDW orders; initial monitoring assurance; no local treatment milestone.
Read official response · PDF page 2Joint monitoring includes UCMR3/5 and DDW orders; initial monitoring assurance; no local treatment milestone. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 2. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue stated OCWD-linked PFAS monitoring program, including cited UCMR3/5 and DDW orders; OCWD policy funds 100% design/construction and 50% eligible O&M where described. No universal local treatment-completion date inferred. Source status: claimed-ongoing; not independently verified. Owner: City of Fountain Valley. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
Yorba Linda Water District
Agency position unclearJoint UCMR/orders monitoring; OCWD pilot at YLWD headquarters and treatment for all groundwater with cost-share policy.
Read official response · PDF page 2Joint UCMR/orders monitoring; OCWD pilot at YLWD headquarters and treatment for all groundwater with cost-share policy. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 2. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue stated OCWD-linked PFAS monitoring program, including cited UCMR3/5 and DDW orders; OCWD policy funds 100% design/construction and 50% eligible O&M where described. No universal local treatment-completion date inferred. Source status: claimed-ongoing; not independently verified. Owner: Yorba Linda Water District. Timing: Not specified.
- Respondent reports: Treat all service-area groundwater; pilot program at headquarters. Source status: claimed-completed; not independently verified. Owner: Yorba Linda Water District. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Anaheim
Agency says implementedNine operating sites/14 wells Phases A/B; four wells at four locations rehabilitating; Phase C design, construction late 2026, operation by July 1, 2029.
Read official response · PDF page 3Nine operating sites/14 wells Phases A/B; four wells at four locations rehabilitating; Phase C design, construction late 2026, operation by July 1, 2029. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF pages 3–4. Engagement is not independent factual, legal or implementation verification.
- Respondent describes: Nine operational treatment locations/14 wells Phases A/B; four wells/four locations rehabilitating and Phase C construction late 2026, operational by July 1, 2029. Source status: partially-implemented; not independently verified. Owner: City of Anaheim. Timing: 2029-07-01.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Garden Grove
Agency says implementedImplementation claim with year only, no action summary.
Read official response · PDF page 2Implementation claim with year only, no action summary. Explicit assent/general principle alone does not supply an implementation disposition or sufficient action detail. Physical report PDF page 37; selected response PDF page 2. Engagement is not independent factual, legal or implementation verification.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Seal Beach
Agency says implementedOCWD monitors for members; no surface-water source facilities. Exceedance prompts evaluation/appropriate actions, not necessarily treatment alone.
Read official response · PDF page 2OCWD monitors for members; no surface-water source facilities. Exceedance prompts evaluation/appropriate actions, not necessarily treatment alone. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF pages 2–3. Engagement is not independent factual, legal or implementation verification.
- Conditional offer: Evaluate and implement appropriate response actions if source exceeds applicable PFAS response levels/thresholds. Conditions/limits: No city surface-water source facilities; OCWD monitors groundwater. Not unconditional promise treatment only. Source status: conditional-future; not independently verified. Owner: City of Seal Beach. Timing: No city surface-water source facilities; OCWD monitors groundwater. Not unconditional promise treatment only..
This review evaluates the response document. Implementation claims have not been independently verified.
City of Tustin
Agency says implementedOCWD monitoring, UCMR3/5/orders, pilots and capital/O&M policy described; no local completion schedule.
Read official response · PDF page 2OCWD monitoring, UCMR3/5/orders, pilots and capital/O&M policy described; no local completion schedule. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 2. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue stated OCWD-linked PFAS monitoring program, including cited UCMR3/5 and DDW orders; OCWD policy funds 100% design/construction and 50% eligible O&M where described. No universal local treatment-completion date inferred. Source status: claimed-ongoing; not independently verified. Owner: City of Tustin. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Newport Beach
Agency says implementedCity/OCWD monitoring, online testing results and non-detect distribution water; OCWD pilot/cost-share policy described.
Read official response · PDF page 3City/OCWD monitoring, online testing results and non-detect distribution water; OCWD pilot/cost-share policy described. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF pages 3–4. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue monitoring/testing and posting all PFAS testing data online; no distribution-system detections claimed. Source status: claimed-ongoing; not independently verified. Owner: City of Newport Beach. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
East Orange County Water District
Agency position unclearCites decade monitoring, UCMR3/5 and DDW orders; local treatment timing not specified.
Read official response · PDF page 2Cites decade monitoring, UCMR3/5 and DDW orders; local treatment timing not specified. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF page 2. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: Continue stated OCWD-linked PFAS monitoring program, including cited UCMR3/5 and DDW orders; OCWD policy funds 100% design/construction and 50% eligible O&M where described. No universal local treatment-completion date inferred. Source status: claimed-ongoing; not independently verified. Owner: East Orange County Water District. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.
City of Fullerton
Agency position unclearBare agreement, no implementation status or action summary.
Read official response · PDF page 2Bare agreement, no implementation status or action summary. Explicit assent/general principle alone does not supply an implementation disposition or sufficient action detail. Physical report PDF page 37; selected response PDF page 2. Engagement is not independent factual, legal or implementation verification.
This review evaluates the response document. Implementation claims have not been independently verified.
Irvine Ranch Water District
Agency says implementedAll-source monitoring; 2018 positive well shutdown until treatment and return to service; alternatives include pausing sources, blending or treatment.
Read official response · PDF page 4All-source monitoring; 2018 positive well shutdown until treatment and return to service; alternatives include pausing sources, blending or treatment. Engages recommendation with actions, conditions, timing or explained refusal; engagement is not implementation verification or legal ruling. Physical report PDF page 37; selected response PDF pages 4–5. Engagement is not independent factual, legal or implementation verification.
- Respondent reports: All-source PFAS monitoring; 2018 positive well shut down until treatment and returned to service. Conditions/limits: Approach may pause sources, blend or treat; no detect in delivered water does not mean all source samples non-detect. Source status: claimed-completed; not independently verified. Owner: Irvine Ranch Water District. Timing: Not specified.
This review evaluates the response document. Implementation claims have not been independently verified.