Recommendation Follow-up T1
Table 1, Continued Technology and Software Lessons — unnumbered Analysis request; editorial reference
BOS should provide a detailed update on the progress of the implementation of the Tyler Enterprise Permitting System, within (3) months.
Jury report: Compliance and Continuity Report: Past Examination, Present Action · PDF page 20
Permanent linkOfficial response
Mariposa County Board of Supervisors
Agency says implementedMariposa County Board of Supervisors: Says Tyler went live in December 2024 for Building and Planning, with Environmental Health expected in early 2026.
Read official response · PDF page 7The update separates live departments from the remaining conversion and gives a target window.
This review evaluates the response document. Implementation claims have not been independently verified.