City of Sebastopol’s Water and Sewer Systems – Deferred Action Has Consequences

Examines utility cost allocation, rate studies, enterprise-fund resources, deferred infrastructure work and public oversight. The jury’s estimate of historical overallocation is not an independently verified liability.

Response available · Sebastopol City Council

Sebastopol City Council response

The City partly agrees with the findings, describes revised allocation and rate studies, and says historical overallocation needs further analysis. It cites loan forgiveness, new studies and efforts to recruit accounting expertise for the oversight committee.

See the synthesis and item-by-item audit

About this overview

This page provides a plain-language orientation to the report and connects it with related civic questions. The official PDF is the authoritative source for complete findings, recommendations, responses, and context.