Ongoing cost without a final policy decision

What should residents consider about Finding dem-F9: Ongoing cost without a final policy decision, and the County’s response?

Office of the Mayor; Department of Emergency Management; San Francisco Public Works; Board of SupervisorsAudit assessment: Addressed
Participate in this discussion

Audit context

What the response says and how it was assessed

Response says

DEM agrees that the unresolved, inoperable system produces continuing cost without progress toward restoration or confirmed retirement.

Audit analysis

The response accepts the full status-quo finding. It gives no cost accounting or evidence of a subsequent institutional decision.

Finding-response score

Document completeness and usefulness—not factual verification or a legal conclusion.

6/10

4/4

Statutory elements

Stated position
2/2
Applicable disagreement elements
2/2

2/6

Public usefulness

Coverage
2/2
Reason specificity
0/2
Support traceability
0/2

The F9 row expressly agrees without qualification. Its explanation is blank, so no cost reasoning or documentary basis can be credited.

Scoring confidence: high

Public participation

Discuss the finding and response

Use Pol.is to discuss both the Grand Jury finding and the County’s response, see where participants agree, and add a perspective for others to consider. Participant statements do not alter this audit or verify factual claims made by any participant or source document.

Loading the Pol.is conversation...
Open on Pol.is